Blue Ridge Parkway

The Linn Cove Viaduct curving around the flank of Grandfather Mountain on slim piers, late-autumn forest in rust and grey, blue ridges fading to the horizon under soft cloud

Photograph: Ashley Knedler · CC0 · cropped

The Blue Ridge Parkway was a road built to put people to work: approved in 1933, begun in September 1935 near Cumberland Knob, North Carolina, and built by private contractors, Italian and Spanish stonemasons and thousands of Civilian Conservation Corps enrollees. It took until 1987 to finish, when a concrete viaduct built from the top down so as not to scar Grandfather Mountain closed the last gap. It is 469 miles long, has no entrance fee, and is open all year, except where weather or repairs close it. In September 2024 Hurricane Helene closed all of it. By 5 October 2026 the Park Service had reopened 458 miles, with the last eleven, between NC 80 and Mount Mitchell State Park, due to be finished by the end of 2026.

Where
Virginia and North Carolina
United States
Start / end
Rockfish Gap, VA (milepost 0) to US 441, NC (milepost 469)
Length
469 mi / 754.8 km (NPS; FHWA)
Designation
All-American Road (FHWA); a national parkway
Season
Open all year; sections close for weather and repairs
Fees
No entrance fee (NPS)
Status
Closed MP 344.2–355.3 (Helene) and MP 76.4–85.9 (weather cleanup); detour at MP 63.5–63.9 (NPS, 13 Oct 2026)
Advisory
United States
(no State Department level)
From Tally’s diary

Mountains fading away in rows, each one paler than the last, and the road running along the very crest with farms and fences dropping away on either side. No lorries, no signs selling anything, just stone tunnels and an overlook every few minutes. Somewhere in the middle a ribbon of concrete curled out round the side of a peak, holding on to nothing I could see.

Route facts

Route
Rockfish Gap, Virginia (milepost 0) to US 441 at Great Smoky Mountains National Park, North Carolina (milepost 469)
Length
469 miles (754.8 km, the Federal Highway Administration’s conversion)Checked · National Park Service, Blue Ridge Parkway
Season window
Open all year; sections close for weather and repairsChecked · National Park Service, Blue Ridge Parkway: road status and closures
Closures
Partly closed as read On 13 October 2026, milepost 344.2 to 355.3 (Hurricane Helene damage) and 76.4 to 85.9 (temporary, weather-related cleanup) were closed, with a signed detour around the James River Bridge at milepost 63.5 to 63.9.Live alert: National Park Service, Blue Ridge Parkway: road status and closures
Fees
No entrance fee; fees are charged for campingChecked · National Park Service, Blue Ridge Parkway: frequently asked questions
Cost to enter
Free
Anchor point
Linn Cove Viaduct
36.10° N, 81.81° W

The short answer

The Blue Ridge Parkway is a two-lane road of 469 miles along the crests of the Blue Ridge and neighbouring ranges, from Rockfish Gap in Virginia (milepost 0), where the Skyline Drive through Shenandoah National Park ends, to US 441 at Great Smoky Mountains National Park in North Carolina (milepost 469). It is a national parkway run by the National Park Service, with no entrance fee, and the Federal Highway Administration lists it as an All-American Road. The road is open all year, but sections close for weather and repairs. As of 7:35 a.m. on 13 October 2026, the Park Service listed two closed sections: milepost 344.2 to 355.3, from NC 80 to Mount Mitchell State Park, still shut by Hurricane Helene damage, with recreation of any kind prohibited; and milepost 76.4 to 85.9 in Virginia, from the Apple Orchard parking area to VA 43 at the Peaks of Otter, closed temporarily for weather-related cleanup. On 5 October the Park Service said 458 of the 469 miles had reopened after Helene.

Why it's worth knowing

A road for hard times. The Park Service traces the idea to Franklin Roosevelt’s visit to the new Skyline Drive in 1933, and Senator Harry Byrd’s suggestion to extend it to the Great Smoky Mountains. Interior Secretary Harold Ickes approved the “park-to-park” highway as a public works project on 24 November 1933 and hired the landscape architect Stanley Abbott to oversee it. Asheville lobbied hard to bring the route through the city instead of through Tennessee, and won; construction began on 11 September 1935 near Cumberland Knob. About 170 miles were open when the United States entered the Second World War.

The missing link. The Park Service’s Mission 66 programme finished everything except 7.7 miles around Grandfather Mountain, whose owner, Hugh Morton, objected to the planned cut on the grounds of the mountain’s ecology, the Park Service says. The answer was the Linn Cove Viaduct, built from the top down so that nothing but its seven piers touched the ground. It opened in 1987, completing the continuous 469-mile route.

Closed end to end. In September 2024 Hurricane Helene brought up to 30 inches of rain and winds up to 60 mph to parts of the Parkway, the Park Service says: 100 percent of the 469 miles closed, thousands of trees came down and 58 catastrophic landslides tore away sections of road. The heaviest damage lay between Linville Falls, near milepost 317, and Mount Mitchell State Park, near milepost 355. By 5 October 2026 the Park Service counted 48 of 60 slide repairs complete and 458 miles restored; the final repairs, from milepost 344 to 355, are slated for completion by the end of 2026. (Its Helene page counts 58 catastrophic landslides; its release counts 60 slide repairs.)

The field notes

Two lengths for one bridge

The Park Service’s own pages disagree about the Linn Cove Viaduct. Its history page gives 1,243 feet and a completion date of 1983; its visitor page gives 1,234 feet and says the viaduct was completed in 1982, with the roadwork around it continuing until it opened in 1987. Both agree on 153 precast concrete segments, on construction from the top down, and on the ribbon-cutting that completed the Parkway on 11 September 1987.

What else is closed

On 13 October 2026 the Park Service also listed: the James River Bridge, milepost 63.5 to 63.9 in Virginia, closed for rehabilitation with a signed detour from milepost 61.4 to 64; the Peaks of Otter Lodge, inside the temporary weather closure at milepost 76.4 to 85.9; the Roanoke Mountain Loop, closed until further notice; Linville Falls Campground and Picnic Area, closed after Helene; Crabtree Falls Campground, closed, with hiking prohibited at Crabtree Falls; and the Linn Cove Visitor Center, temporarily closed. Its 5 October release had reported that drivers could again go uninterrupted from milepost 63.7 in Virginia to Little Switzerland, near milepost 344, in North Carolina; the weather closure listed on 13 October interrupts that stretch for now. The section from Soco Gap to US 441, milepost 455.7 to 469.1, closed for weather on 12 October, was listed as open again on 13 October.

Tally’s list
  1. Pull right into the overlook to look. The person behind you lives here and has seen it.
  2. Go when the leaves turn, and go on a weekday. Everyone else has had the same idea about the weekend.
  3. Name every overlook. (Gave up. They have their names on little signs already, and have been very patient with me.)
  4. Look at the viaduct from below as well as from on top.
  5. Check which miles are open the night before, and plan the day around the gaps.
The Relic

The Linn Cove Viaduct. A concrete bridge that carries the Blue Ridge Parkway around the boulder-strewn side of Grandfather Mountain, North Carolina, at milepost 304, in a long S-curve on seven piers. Its 153 segments, each about 50 tons, were cast a few miles away, each against the one before it, and lowered into place from the end of the bridge already built, so that no road and no heavy machinery had to touch the slope; only the ground under the deck was cleared, and the concrete was tinted with iron oxide to match the rock. Only one segment, the southernmost, is straight. The Park Service’s pages give its length as 1,243 and as 1,234 feet. Drivers may not stop or walk on it; overlooks and trails nearby give the view.

Tally, in the marginI drove over it without knowing, then went back and looked at it from underneath for an hour. It barely touches the mountain at all, which seems to have been the whole point, and a very polite one.

Getting there

How to drive it. The north end is at Rockfish Gap, off I-64 in Virginia, where the Skyline Drive heads north and the Parkway south. The south end meets US 441 at Great Smoky Mountains National Park, North Carolina. Many roads cross it, and the Park Service’s road status page lists the open sections by milepost and crossroad. FHWA allows four days to enjoy the whole road.

When to go. The Park Service says autumn colour typically develops in mid to late October, and that Catawba rhododendron blooms from early June around the Peaks of Otter to the third week of June at Craggy Gardens. Most visitor centres, campgrounds and picnic areas open only from spring to autumn; the Blue Ridge Parkway Visitor Center and the Folk Art Center near Asheville are open all year.

What to arrange ahead. Nothing for the road: there is no entrance fee. Campsites can be reserved on Recreation.gov, except at Crabtree Falls. Check the Park Service’s road status page the day before, and allow for the 2026 closures above.

Safety. The State Department’s travel advisories cover other countries, so none applies here. The Park Service warns that mobile phones do not work in many places and GPS can be unreliable, that some curves tighten as you go through them, that sleeping overnight in a vehicle at an overlook is not allowed, and that the Parkway is bear country.

Mark this place

North America →

Common questions

Is the Blue Ridge Parkway open?

Mostly. On 13 October 2026 the National Park Service listed the Blue Ridge Parkway closed from milepost 344.2 to 355.3, NC 80 to Mount Mitchell State Park, because of Hurricane Helene damage, and from milepost 76.4 to 85.9 in Virginia, near the Peaks of Otter, temporarily for weather-related cleanup. On 5 October it said 458 of the 469 miles had reopened after Helene.

When will the Blue Ridge Parkway fully reopen after Hurricane Helene?

The National Park Service said on 5 October 2026 that the final Hurricane Helene road repairs on the Blue Ridge Parkway, from milepost 344 to 355 in North Carolina, were slated for completion and reopening by the end of 2026.

How long is the Blue Ridge Parkway?

The Blue Ridge Parkway is 469 miles (754.8 km) long, from Rockfish Gap in Virginia, milepost 0, to US 441 at Great Smoky Mountains National Park in North Carolina, the National Park Service and the Federal Highway Administration say.

Is there a fee to drive the Blue Ridge Parkway?

No. The National Park Service charges no entrance fee for the Blue Ridge Parkway. It charges fees for camping, with half price on camping fees for holders of Interagency Senior and Access passes.

When is the best time to see fall colour on the Blue Ridge Parkway?

The National Park Service says fall colour on the Blue Ridge Parkway typically develops in mid to late October, though many factors change when and where colour peaks in a given year.

Is the Blue Ridge Parkway a national park?

Not technically. The National Park Service calls the Blue Ridge Parkway a national parkway, not a national park, though the Park Service runs both. It joins Shenandoah National Park’s Skyline Drive at Rockfish Gap and ends at Great Smoky Mountains National Park.

What is the Linn Cove Viaduct?

The Linn Cove Viaduct is a curving concrete bridge of 153 precast segments that carries the Blue Ridge Parkway around Grandfather Mountain at milepost 304, North Carolina. Built from the top down to protect the mountain, it was the last link of the Parkway, which was dedicated as complete on 11 September 1987.

When was the Blue Ridge Parkway built?

Construction of the Blue Ridge Parkway began on 11 September 1935 near Cumberland Knob, North Carolina, the National Park Service says. Most of it was finished by the 1960s; the last link, the Linn Cove Viaduct around Grandfather Mountain, opened in 1987.

Notes on sources. This entry draws on the National Park Service’s Blue Ridge Parkway pages, read directly on 13 October 2026. Road Status and Closures (as of 1:59 p.m., 12 October 2026, and read again as of 7:35 a.m., 13 October 2026) supplied every closure by milepost and the facility closures, including the Soco Gap section that was closed on the 12th and open on the 13th. The park’s home page supplied the 469 miles. Helene Impacts and Recovery supplied the storm figures (up to 30 inches of rain, winds up to 60 mph, 100 percent closed, 58 catastrophic landslides), the worst-hit stretch from milepost 317 to 355 and the end-of-2026 estimate. The release of 5 October 2026 supplied 458 of 469 miles, 48 of 60 slide repairs, the uninterrupted stretch from milepost 63.7 to Little Switzerland and the final repairs from milepost 344 to 355. The FAQ supplied the national parkway status, the Skyline Drive junction, the builders, the absence of an entrance fee and the camping discount, year-round opening, the fall colour and rhododendron timings, campground booking, and the warnings on phones, curves, overnight sleeping and bears. Construction of the Parkway supplied Roosevelt, Byrd, Ickes and 24 November 1933, Abbott, the Asheville route, 11 September 1935 at Cumberland Knob, the 170 miles open at the war, Mission 66, the 7.7 miles at Grandfather Mountain and Hugh Morton. The two Linn Cove Viaduct pages supplied its two lengths and dates, the 153 segments of 50 tons, match casting, top-down construction, seven piers, the tinted concrete, the one straight segment, milepost 304, the bar on stopping and the dedication of 11 September 1987. The Federal Highway Administration’s America’s Byways page (fhwaapps.fhwa.dot.gov/bywaysp) supplied the All-American Road listing, 469 miles (754.8 km), no fee and four days. Stop coordinates are from the US Geological Survey’s Geographic Names Information System, and for the Linn Cove Viaduct and the Peaks of Otter from Wikipedia. Checked 13 October 2026. Written and fact-checked by SockMonkey.com. Last reviewed 13 October 2026.